Project Progress Report (PPR) – Submission (2024-04-22 08:57:11)

Date : 2024-04-22
Project Code : J2419
Job Title : TO SUPPLY TRUNKING WITH SEPARATOR AND COVER AND RAMP CHEQUARED PLATE
Purchase Order Status : P.O RECEIVED
Name of Coordinator : FADHIL ASHRAFF BIN AB RAHIM
Subcontractor / Supplier : G I F INDUSTRIAL (M) SDN BHD
REXCELLYNK TECH SDN BHD
Project Update / Real Time Status : jotform_untitled_markdown19.4.2024 – Received ramp chequared plate from REXCELLYNK TECH SDN BHD. Material have been check and handover to client.

20.4.2024 – Received trunking from GIF Industries Sdn Bhd. Material have been delivered to client.

PROJECT STATUS : HANDOVER COMPLETED BUT WAITING D.O/W.O
EXPECTED PROJECT COMPLETION : 22.4.2024/CW17
UPLOAD FILES/PICTURE :