Project Progress Report (PPR) – Submission (2024-04-20 10:44:00)

Date : 2024-03-29
Project Code : J2413
Job Title : BS HONSEL RIVET GUN
Purchase Order Status : P.O RECEIVED
Name of Coordinator : SRI HAREE A/L SUBRAMANIAM
Subcontractor / Supplier : Darash Maju Pekan
Project Update / Real Time Status : jotform_untitled_markdown-Rivdom eBZ 3 battery blind rivet tool for high-strength blind rivets ordered from Germany to deliver MBM Pekan. Total quantity is 5 pcs.

Specifications as follow:
Rivdom eBZ 3 battery blind rivet tool for high-strength blind rivets 6.4 + 7.8 mm with 2 batteries 20V (2.0 Ah), quick charger (220V/50-60HZ) type G (UK) in L-Boxx.
-Will be delivered on 22/4/24 to MBM Pekan, PIC receiveing the items is Mr Devan 

PROJECT STATUS : PROJECT IN PROGRESS
EXPECTED PROJECT COMPLETION : 22/4/24
UPLOAD FILES/PICTURE : 41884242_DARASH.pdf