Date : 2024-04-16
Project Code : IS2420
Job Title : FABRICATE JIG FOR BRAKE ASSEMBLY
Purchase Order Status : P.O RECEIVED
Name of Coordinator : SRI HAREE A/L SUBRAMANIAM
Subcontractor / Supplier : Infinite Tooling Sdn Bhd
Project Update / Real Time Status : jotform_untitled_markdown- Jig have been assembled by IT on 8/4/24
– Jig have been inspected using checklist by Vesa on 12/4/24 and safety cable was not installed, other requirements fulfilled
– Jig have been installed with safety cable and and seating area is modified a bit due knuckle is not sitting properly
– Jig delivered to HQ DM on 16/4/24
-Jig will be installed on 22/4/24 at MMC
PROJECT STATUS : PROJECT IN PROGRESS
EXPECTED PROJECT COMPLETION : 26/4/24
UPLOAD FILES/PICTURE : DM_BRAKE ASSY JIG Drawing.pdf