Skip to content Skip to footer

Project Progress Report (PPR) – Submission (2024-04-17 12:51:07)

Date : 2024-04-17
Project Code : IS2423
Job Title : CONCRETE SLAB TEST
Purchase Order Status : P.O RECEIVED
Name of Coordinator : MOHAMAD IZUAN BIN IZZUDIN
Subcontractor / Supplier : Tp Geotechnic Sdn Bhd
Project Update / Real Time Status : jotform_untitled_markdown

Progress:
1. Measuring and marking all 6 locations for coring spot was done.
2. Few locations were relocated and marked as per MMC requested.
Pending:
1. Power supply and water supply location will be confirm and inform by Shauqy  on18/4/2024.
2. Redraw the drawing for new coring location.

PROJECT STATUS : PROJECT IN PROGRESS
EXPECTED PROJECT COMPLETION : 3.5.2024/CW18
UPLOAD FILES/PICTURE : IMG-20240417-WA0010.jpg
IMG-20240417-WA0011.jpg
IMG-20240417-WA0012.jpg
IMG-20240417-WA0013.jpg
IMG-20240417-WA0014.jpg
IMG-20240417-WA0016.jpg
IMG-20240417-WA0017.jpg
IMG-20240417-WA0018.jpg
IMG-20240417-WA0019.jpg

Leave a comment