Project Progress Report (PPR) – Submission (2024-04-16 14:36:43)

Project Code : IS2419
Job Title : CONSUMABLE ITEM
Purchase Order Status : P.O RECEIVED
Name of Coordinator : MOHAMAD IZUAN BIN IZZUDIN
Subcontractor / Supplier : LT Paint & Thinner, Kuantan
Project Update / Real Time Status : jotform_untitled_markdown

**Delivery IS2419 (PO-01388)**
1. WD-40 ANTI RUST SPRAY 24pcs ✅
**2. THINNER 13L 1tin ✅**
3. FUSE PLUG 13A 10pcs✅
4. 16MM WRENCH RO-16-25 2pcs (pending 1pcs) REMAINING ITEM ETA -CW 17

5. BOSCH BATTERY CHARGER GAL12V-40 1pcs✅
6. SMC PNEUMATIC STRAIGHT FITTING 8MM 10pcs ✅
7. SMC PNEUMATIC STRAIGHT FITTING 6MM 10pcs✅

PROJECT STATUS : PROJECT IN PROGRESS
EXPECTED PROJECT COMPLETION : 26/4/2024
UPLOAD FILES/PICTURE : IS2419_HANDOVER_4.pdf
Date : 2024-04-16