Project Progress Report (PPR) – Submission (2024-03-13 17:01:41)

Date : 2024-03-13
Project Code : M2406 – 12 V Battery Supply
Job Title : 12 V Battery Supply
Purchase Order Status : P.O RECEIVED
Name of Coordinator : JAYA VICKNESSVAR A/L JAYA KUMAR
Subcontractor / Supplier : Avertec Sdn Bhd
Shopee (Online Purchase)
Project Update / Real Time Status : jotform_untitled_markdownJob Status :

1. PO From MBM received
2. Supplier : Avertec, Shoppee
3. Job Status : In PO issuance phase to supplier
4. ETA completion : 27th March 2024
PROJECT STATUS : PROJECT IN PROGRESS
EXPECTED PROJECT COMPLETION : 27/3/24