Project Progress Report (PPR) – Submission (2024-03-12 14:44:39)

Project Code : J2404
Job Title : FLOOR COMP ELECTRICAL PART REPLACEMENT
Purchase Order Status : P.O RECEIVED
Name of Coordinator : MUHAMMAD AMMAR FIKRI BIN ROSLEE
Subcontractor / Supplier : REXCEL HEAVY ENGINEERING (M) SDN BHD
Project Update / Real Time Status : jotform_untitled_markdownDO AND HANDOVER SIGNED;

FLOOR COMP ELECTRICAL PART REPLACEMENT 70% UPON COMPLETE

PROJECT STATUS : PROJECT COMPLETED PROCEED INVOICING
EXPECTED PROJECT COMPLETION : 1/3/2024
UPLOAD FILES/PICTURE : DO_FLOOR COMP.pdf
HANDOVER FLOOR COMP.pdf
Date : 2024-03-04