Project Code : J2346
Job Title : ADAPTER FOR DOUBLE EXHAUST PIPE Y-JUNCTION WITH INSTALLATION
Purchase Order Status : P.O RECEIVED
Name of Coordinator : MUHAMMAD AMMAR FIKRI BIN ROSLEE
Subcontractor / Supplier : Nederman (Malaysia) Sdn. Bhd.
Project Update / Real Time Status : jotform_untitled_markdownDELAY ISSUE:
Update that the shipment vessel will take a longer time to arrive to Malaysia due to a new routing for Sea shipment which will not pass through the Suez Canal due to the nearby war. The new Sea route will take a longer route which will pass through the region of Afrika and then to Asia. The Vessel is currently at Gulf of Guinea and the updated ETA is 16th April 2024.
PROJECT STATUS : PROJECT IN PROGRESS
EXPECTED PROJECT COMPLETION : 20/04/2024
UPLOAD FILES/PICTURE :
Date : 2024-02-23