Date : 2024-01-19
Project Code : J2402
Job Title : CROWN BOXES MOVEMENT BACK TO MBSM
Purchase Order Status : P.O RECEIVED
Name of Coordinator : VESAKAN A/L M. GANESAN
Subcontractor / Supplier : Darash Maju Kajang
Project Update / Real Time Status : jotform_untitled_markdown
1) On January 15, 2024, the project took place at MBSM.
2) The project was completed within a single day.
3) Successfully relocated all the crown boxes from LG1 MBSM to Level 3.
PROJECT STATUS : PROJECT COMPLETED PROCEED INVOICING
EXPECTED PROJECT COMPLETION : 15/01/2024
UPLOAD FILES/PICTURE : CamScanner 01-17-2024 12.19.pdf