Project Progress Report (PPR) – Submission (2024-01-08 16:13:04)

Submission Date : 2024-01-08 16:13:04
Project Code : J2336
Job Title : OVERHEAD HANGER CRANE
Purchase Order Status : P.O RECEIVED
Name of Coordinator : MUHAMMAD AMMAR FIKRI BIN ROSLEE
Subcontractor / Supplier : INTERFACE SOLUTIONS CO.,LTD.
Project Update / Real Time Status : jotform_untitled_markdownHMSB will **proceed with drawing approval** exclude commented items:

* HMSB need Autocad Drawing for conveyor system, they need it for JKKP registration.

__DM will email AutoCAD top view drawing.__

* HMSB need us to revised spec for light curtain follow according to HMSB spec.

__DM’s Supplier now using the length of 1280mm.__

* The position for trunking

__Will be checked and revised.__

* · FRL pressure switch not include in input PLC drawing.

*              __Will be check.__
PROJECT STATUS : PROJECT IN PROGRESS
EXPECTED PROJECT COMPLETION : 13/2/24