Project Progress Report (PPR) – Submission (2023-12-31 15:44:50)

Submission Date : 2023-12-31 15:44:50
Project Code : J2345
Job Title : HapSeng Refurbish Jig & New jig
Purchase Order Status : P.O RECEIVED
Name of Coordinator : SRI HAREE A/L SUBRAMANIAM
Subcontractor / Supplier : Infinite Tooling Sdn Bhd
Project Update / Real Time Status : jotform_untitled_markdown4 jigs have completed installed with new linear guide block:

1. Backside Assy LH
2. Backside Assy RH
3. Front Assy jig
4 Under Body Assy jig 2
Discussion with Mr Lee and team on fabrication process for new base for new jig, list standard parts to be purchased by DM and castor wheel. (Refer attached minutes of meeting)
Confirmed schedule with Jeevan to install tubing on 29/12/23-1/01/2024 after received SMC parts 
Confirmed order for rotary joint 3pcs from Takeda works and pillow block 3pcs from SLS Bearings for the new base for new jig 

PROJECT STATUS : PROJECT IN PROGRESS
EXPECTED PROJECT COMPLETION : 13/1/2024
UPLOAD FILES/PICTURE : IMG_20231226_145805.jpg
IMG_20231227_095611.jpg
IMG_20231227_101056.jpg
MEETING MINUTE J2345 28122023.pdf